The sun was blazing and the heat was rising. In recent days, the temperature in most areas is high, in order to ensure the orderly and powerful promotion of the project, the first-line construction staff of Wanhao is not afraid of the hot summer, and always stick to the post. They are the "most beautiful" workers in this hot summer.
Recently, the progress of the steel film structure project in the Malian Desert Park in Dingbian, Shaanxi Province has been refreshed, and then let's take a look at its engineering progress today
As of July 20:
1, the west Gate film has been fully installed, is in the process of painting anti-rust, film cleaning and cutting and other work;
2. The north gate is installing the membrane material in area A, and the tension work of the membrane material has been carried out in the past two days, which is expected to be completed within this week.
From the local scene of the project, it can be seen that the construction personnel are not only fast but also very neat and careful in construction.
Since the start of the project, Wanhao engineering team docking construction, focusing on high quality, steady progress, risk prevention, overall promotion of project construction.
The owner has given us strong support and recognition, and all departments of the company have closely coordinated and cooperated, and our engineering department can be fully implemented. The current construction is in line with the expected progress, and we have the ability, confidence and determination to complete the project on time with quality and quantity." Dingbian Malian beach desert park steel film structure project manager confidently said.
It is reported that since the construction of the project, it has been affected by a variety of adverse construction weather, such as sandstorms, heavy rain and hot summer, which has a great impact on the site construction. In order to continue to do a good job in element guarantee, supervision and inspection, Wanhao site construction personnel implemented the special responsibility system, closely focused on nodes, reverse time, wall chart operations, accelerate the project progress, and promote the construction of multiple nodes simultaneously.
Next, all parties of Wanhao will seize the good weather, race against time to seize the schedule, and complete the project construction with high quality, high standards and high efficiency.
Every day brings something new, and every moment brings the project closer to completion.